Website Schedule Update July 2015

Schedule

The Bentonville Municipal Airport Master Plan Update will be completed on a 12-month schedule. The project began in October 2014 and will submitted to the FAA by October 2015. The graphic below depicts the project schedule and its progress through July 2015.

 

Public Workshops

Three public workshops will be held throughout the development of the project to provide citizens with an opportunity to provide input. The timing of the workshops is as follows:

 

October 2014 Summary - 10/17/2014 Meeting Media - 10/17/2014 Meeting
     
February 2015 Summary - 2/3/2015 Meeting Boards - 2/3/2015 Meeting
     
August 2015