This project consists of widening Watertower Rd. to four lanes with a median from Hwy 102 to SE 6th St. and constructing 8th St. from Watertower Rd. west to connect to the new 8th St. / I-49 interchange. This project is funded with street bond funds.

PROJECT UPDATES

 

March 16, 2016 - We are currently 30% along with design and the City intends to begin construction by summer 2017. The current design includes a roundabout at the intersection of Watertower Rd. and 8th St.